3 persons weave 168 shawls in 14 days, how many shawls will 8 people weave in 5 days?
  1. 90
  2. 105
  3. 115
  4. 160

A
115
B
90
C
105
D
160
Solution
Verified by Toppr

b'
Set the proportion for number of persons with the number of shawls. Both the quantities are in direct ratio.
Here, we are asked to find out the number of shawls, we compare each item with the number of shawls as shown below :
More number of persons More shawls
Less number of persons Less shawls
i.e. the relationship is direct.
Also, More number of days More shawls
Less number of days Less shawls
i.e. the relationship is direct.
Persons 3 : 8 : : 168 : x
Days 14 : 5

Was this answer helpful?
0
Similar Questions
Q1
3 persons weave 168 shawls in 14 days, how many shawls will 8 people weave in 5 days?
View Solution
Q2

If 3 people can weave 168 shawls in 14 days, how many shawls will be woven by 8 people in 5 days?


View Solution
Q3

If 3 person can weave 168 shawls in 14 days, how many shawls will be woven by 8 persons in 5 days?


View Solution
Q4
Reema weaves 35 baskets in 25 days. In how many days will she weave 55 baskets?
View Solution
Q5

Seema weaves 25 baskets in 35 days. In how many days will she weave 110 baskets?


View Solution