$$30$$ persons can reap a field in $$17$$ days. How many more persons should be engaged to reap the same field in $$10$$ days?

Solution
Verified by Toppr

$$17$$ days need reap the field by $$=30$$ persons
$$1$$ days need to reap the field by more man $$=30\times 17=510$$
$$10$$ days need to reap filed by less men $$=\dfrac{510}{10}=51$$ men $$=\dfrac{510}{10}=51$$ men

Was this answer helpful?
0
Similar Questions
Q1

Question 88

30 persons can reap a field in 17 days. How many more persons should be engaged to reap the same field in 10 days?

View Solution
Q2
30 persons can reap a field in 17 days.How many more persons should be engaged to reap the same field in 10 days?
View Solution
Q3
30 persons can reap a field in 17 days. How many more persons should be engaged to reap the same field in 10 days?
[3 marks]
View Solution
Q4

Question 88

30 persons can reap a field in 17 days. How many more persons should be engaged to reap the same field in 10 days?


View Solution
Q5
16 men can reap a field in 30 days. How many men must be engaged to reap the same field in 24 days?
View Solution