Question

A and B can do a piece of work in 30 days. While B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days before B and C leave. How many days more will A take to finish the work?
  1. 36 days
  2. 18 days
  3. 24 days
  4. 30 days

A
18 days
B
24 days
C
30 days
D
36 days
Solution
Verified by Toppr

(A+B)'s one day's work =130

(B+C)'s one day's work =124..........(1)

(C+A)'s one day's work =120

(A+B+C)'s one day's work =12[130+124+120]=12×[20+25+30600]=751200=116...........(2)

(A+B+C)'s 10 day's work =1016=58

Remaining work, 158=38 (which is done by A)

From (1) and (2), A's one day's work =116124=148

Remaining 38 of the work is done by A alone in 38×48=18 days.

Was this answer helpful?
7
Similar Questions
Q1
A and B can do a piece of work in 30 days. While B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days before B and C leave. How many days more will A take to finish the work?
View Solution
Q2
A and B can do a piece of work in 30 days while B and C can do the same work in 24 days, and C and A can do it in 20 days. They all work together for 10 days before B and C leave. How many more days will A take to finish the work?
View Solution
Q3

A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?


View Solution
Q4

A and B can do a piece of work in 18 days: B and C can do it in 24 days while C and A can finish it in 36 days. In how many days can A. B. C finish it. if they all work together?

View Solution
Q5

A and B take 30 days to finish a work, B and C take 24 days to finish that particular work, C and A take 20 days to finish the same work. All of them can finish the work in 10 days and If B and C leave the job, then how many days does A take to finish the same work?

View Solution