Question

A and B together can do a piece of work in 8 days, but A alone can do it in 12 days. How many days would B alone take to do the same work?

Solution
Verified by Toppr

Work done by A and B together in 1 day =18 of the work
Work done by A in 1 day =112 of the work

Work done by B in 1 day =18112=3224=124

Number of days taken by B alone to do the same work

=1124=24days

Was this answer helpful?
26
Similar Questions
Q1
A and B together can do a piece of work in 8 days, but A alone can do it in 12 days. How many days would B alone take to do the same work?
View Solution
Q2
X and Y together can do a piece of work in 8 days, which X alone can do in 12 days. In how many days can Y do the same work alone?
View Solution
Q3
A alone can do a piece of work in 15 days and B alone can do the same work in 12 days.A works alone for the first four days. In how many days will A and B together finishing the remaining work?
View Solution
Q4
A and B together can do a piece of work in 623 days , but B alone can do it in 10 days. How long will A take to do it alone ?
View Solution
Q5
A alone can do a piece in 10 days and B alone can so it in 15 days. In how many days will A and B together do the same work?
View Solution