A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it ?
  1. 7 days
  2. 3 days
  3. 9 days
  4. 6 days

A
9 days
B
7 days
C
3 days
D
6 days
Solution
Verified by Toppr

Work done by A in 1 day =110

Work done by B in 1 day=115

Work done by A and B in 1 day=110+115=25150

Working together they will complete the work in 15025=6 days

Was this answer helpful?
18
Similar Questions
Q1
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it ?
View Solution
Q2
A can do a piece of work in 15 days while B can do it in 10 days. how long will they take together to do it?
View Solution
Q3

A, B and C can do a piece of work in 10 days. 12 days and 15 days respectively. How long will they take to finish it if they work together?

View Solution
Q4

A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaiing work?

View Solution
Q5
A can do a piece of work in 7 days of 9 hr each, and B can do it in 6 days of 7 hour. How long will they take to do it working together 425 hr a day ?
View Solution