Then A can do the work in one day =110
And B can do the work in one day =118
Then A & B's one day's work =110+118=745
Given A ,B and C did work in 4 days
Then A ,B and C's one day work =14
∴ C one day work=14−745=17180
When only C does work =18017=101017 days.