A can do a piece of work in 12 days and B alone can do it in 16 days.They worked together on it for 3 days and then A left.How long did B take to finish the remaining work ?

Solution
Verified by Toppr


2039326_1260418_ans_353b70d8e3eb42c5a11c343a97021f76.JPG

Was this answer helpful?
2
Similar Questions
Q1
A alone can do a piece of work in 12 days and B alone can do the same work in 16 days. They worked together on it for 3 days and then A left. How long did B take to finish the remaining work?
View Solution
Q2
A can do a piece of work in 12 days and B alone can do it in 16 days. They worked together on it for 3 days and then. A left. how long B take to finish the remaning work?
View Solution
Q3
A and B together can do a piece of work in 16 days and A alone can do it in 48 days. How long will B take to complete the work?
View Solution
Q4
$$A$$ can do a piece of work in $$40$$ days. He works at it for $$8$$ days and then $$B$$ finishes the remaining work in $$16$$ days. How long will they take to complete the work if they do it together?
View Solution
Q5
A can do a piece of work in 623 days and B in 5 days. They work together for 2 days and then A leaves B to finish the work alone. How long will B take to finish it?
View Solution