0
You visited us 0 times! Enjoying our articles? Unlock Full Access!
Question

A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the twice as large as the As work is -
  1. 36
  2. 30
  3. 15
  4. 24

A
15
B
24
C
36
D
30
Solution
Verified by Toppr

A can do a work say w in 24 days
Aw24 (work done by A in one day)
B is 60% more efficient
B1.6×w24 (work done by B in one day)
Now B has to do work 2w
For one day B can do B1.6×w24
Say B takes x days to complete 2w amount of work.
1.6×w24×x=2w
x=481.6=30

Was this answer helpful?
0
Similar Questions
Q1
A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the twice as large as the As work is -
View Solution
Q2
A can do a piece of work in 24 days. If B is 60% more efficient then the number of days required by B to do the twice as large as the earlier work is-
View Solution
Q3
A can do a piece of work in 9 days. B is 50% more efficient than A. The number of days it takes B to do the same piece of work is:
View Solution
Q4
Sharma is 20% less efficient than Kelkar. If Kelkar can do a piece of work in 24 days, then the number of days required by Sharma to complete the same work alone.

View Solution
Q5

A works twice as fast as B. If both of them can together finish a piece of work in 12 days, then B alone can do it in

(a) 24 days

(b) 27 days

(c) 36 days

(d) 48 days

View Solution