0
You visited us 0 times! Enjoying our articles? Unlock Full Access!
Question

A contractor undertakes to dig a canal, 6 kilometers long in 35 days and employed 90 men. He finds that after 20 days only 2 km of canal have been completed . How many more men must be employed to finish the work in time?
  1. 120 men
  2. 180 men
  3. 170 men
  4. 150 men

A
120 men
B
170 men
C
180 men
D
150 men
Solution
Verified by Toppr

Total time given =35 days.

To dig a canal of 2 km in 20 days, 90 men were required.

So, to dig a canal of 1 km in 1 day, 90×202 men will be required.

So, to dig a canal of 4 km in 15 days 900×415 =240 men will be required.

As 90 men were already employed, so 150 more men are required.

Was this answer helpful?
8
Similar Questions
Q1
A contractor undertakes to dig a canal, 6 kilometers long in 35 days and employed 90 men. He finds that after 20 days only 2 km of canal have been completed . How many more men must be employed to finish the work in time?
View Solution
Q2
A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length
of the road has been made . How many more men should he emply so that the work many be complete in time ?
View Solution
Q3
A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men?
View Solution
Q4

A contractor undertakes to build a wall 1000 m long in 50 days. He employs 56 men, but at the end of 27 days, he finds that only 448 m of wall is built. How many extra men must the contractor employ so that the wall is completed in time?

View Solution
Q5

A contractor undertook to build a road in 200 days. He employed 140 men. After 60 days, he found that only one-fourth of the road could be built. How many additional men should he employ to complete the work in time?

View Solution