Question

A particular work can be completed by $$6$$ men and $$6$$ women in $$24$$ days; whereas the same work can be completed by $$8$$ men and $$12$$ women in $$15$$ days. Find:
$$(i)$$ According to the amount of work done, one man is equivalent to how many women.
$$(ii)$$ The time taken by $$4$$ men and $$6$$ women to complete the same work.

Solution
Verified by Toppr

Was this answer helpful?
0
Similar Questions
Q1

A particular work can be completed by 6 men and 6 women in 24 days; whereas the same work can be completed by 8 men and 12 women in 15 days. Find:

i) According to the amount of work done, one man is equivalent to how many women.

ii) The time taken by 4 men and 6 women to complete the same work.

View Solution
Q2
A particular work can be completed by 6 men and 6 women in 24 days, whereas the same work can be completed by 8 men and 12 women in 15 days. Find the time taken by 4 men and 6 women to complete the same work .
View Solution
Q3
24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besides 12 men and 6 women ?
View Solution
Q4
8 women and 12 men can complete a work in 10 days while 6 women and 8 men can complete the work in 14 days. Find the time taken by one women alone and that one man alone can finish the work.
View Solution
Q5
24 men can complete a work in 16 days, 32 women can complete the same work in 24 days. 16 men and 16 women started working and worked for 12 days. How many more men are to be added to complete the remaining work in 2 days?
View Solution