Question

A place of work is done by 6 men & 5 women in 6 day or 3 men and 4 women in 10 days. How many days will it take for 9 men & 15 women to finish that work ?

Solution
Verified by Toppr

we need to get 1 man per day work and 1 woman per day work.
Let 1 man 1 day work =x
and 1 woman 1 day work = y.
6x+5y=16........(1)

3x+4y=110........(2)
On solving (1) and (2) to, we get

x=154andy=190

Hence, (9 men + 15 women)'s 1 days work

=9x+15y

=9×154+15×190

=16+16

=26

=13ans.
Then, 9 men and 15 women will finish the work in 3 days

Was this answer helpful?
0
Similar Questions
Q1
A place of work is done by 6 men & 5 women in 6 day or 3 men and 4 women in 10 days. How many days will it take for 9 men & 15 women to finish that work ?
View Solution
Q2
A piece of work can be done by 6 men and 5 women in 6 days or 3 men and 4 women in 10 days. It can be done by 9 men and 15 women in how many days ?
View Solution
Q3
3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work
View Solution
Q4
4 men and 6 women finish a job in 8 days while 3 men and 7 women finish it in 10 days. In how many days will 10 women working together finish it ?
View Solution
Q5
4 men or 6 women can do a work in 42 days. The number of days 12 men and 3 women would take to finish the work is
View Solution