A takes 6 days less than the time taken by B to finish a piece of work. If both A And B together can finish it in 4 days, find the time taken by B to finish the work.
Suppose B alone takes x days to finish the work. Then A alone can finish it in (x−6) days
Now A's one day's work + B's one day's work =1x+1x−6
and (A+B)'s one day's work =14
∴1x+1x−6=14
⇒x−6+xx(x−6)=14⇒2x−6x2−6x=14
⇒8x−24=x2−6x
⇒x2−14x+24=0
⇒x2−12x−2x+24=0
⇒(x−12)(x−2)=0
⇒x=12orx=2
But x cannot be less than 6.
So x=12
Hence, B also can finish the work in 12 days.