Correct option is A. 2
Let $$x$$ be the number of days required to complete a piece of work by $$125$$ men.
Number of men | $$50$$ | $$125$$ |
Months | $$5$$ | $$x$$ |
Since, the number of men and the number of days taken to do a piece of work are in inverse variation, we have:$$\Rightarrow$$ $$50\times 5=125x$$
$$\Rightarrow$$ $$x=\dfrac{50\times 5}{125}$$
$$\therefore$$ $$x=2$$
$$\therefore$$ The required number of months are $$2.$$