Question

Certain number of persons can complete a work in 100 days. If 10 persons were less, it would have taken 10 days more for the work to be completed. Number of persons in the beginning is
  1. 100
  2. 90
  3. 110
  4. None of these

A
100
B
90
C
110
D
None of these
Solution
Verified by Toppr

Let the person in beginning be x
Then according to question,

x peron do the work in 100 days

x×(100)=(x10)×(110)

100x=110x1100

10x=1100x=110

Was this answer helpful?
2
Similar Questions
Q1
Certain number of persons can complete a work in 100 days. If 10 persons were less, it would have taken 10 days more for the work to be completed. Number of persons in the beginning is
View Solution
Q2
A certain number of men can do a work in 60 days. If there were 8 more men, it could be completed in 10 days less. How many men were there in the beginning?
View Solution
Q3
If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days.
View Solution
Q4
15 persons complete a work in 4 days by working 6 hours a day. How many days will it take to complete the work if 10 persons work 8 hours a day?
View Solution
Q5

If 5 persons can do a work in 10 days, then 10 people can complete the same amount of work in ____days.


View Solution