If 12 men can do a piece of work in 18 days , in how many days will 8 men complete it ?
  1. 12
  2. 27
  3. 10
  4. 163

A
10
B
163
C
12
D
27
Solution
Verified by Toppr

Let the required number of days be x.
Less men, More days (Indirect Proportion)
8:12::18:x
812=18x

8x=12×18

x=2168

x=27days

Required number of days are 27.