Question

If 12 men working 8 hours a day can complete a task in 16 days. If the same task must be completed in 8 days, how many more people would be required if all them work for 12 hours a day?

Solution
Verified by Toppr

a work can be done by
12 men 3 hr in 16 days
same work
men 8 days for 12 hr
So,
w1=w2
m1h1,d1=m2h2d2
12×8×16=m2×8×12
m2=16

1109775_809676_ans_38eb2d6b10634c95861f1a7fcf7b7fe9.jpg

Was this answer helpful?
0
Similar Questions
Q1
If 12 men working 8 hours a day can complete a task in 16 days. If the same task must be completed in 8 days, how many more people would be required if all them work for 12 hours a day?
View Solution
Q2
A man works 8 hours daily and completes a task in 12 days. If he works 6 hours daily, in how many days will the same work be completed?
View Solution
Q3
12 men working 8 hours a day complete a work in 10 days. How long would 16 men working 7 12 hours a day take to complete the same work ?
View Solution
Q4
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
View Solution
Q5
If 20 men working 8 hours per day can complete a piece of work in 21 days. How many hours per day must 48 men work to complete the same job in 7 days
View Solution