If 12 men working 8 hours a day can complete a task in 16 days. If the same task must be completed in 8 days, how many more people would be required if all them work for 12 hours a day?
a work can be done by
12 men 3 hr in 16 days
same work
men 8 days for 12 hr
So,
w1=w2
m1h1,d1=m2h2d2
12×8×16=m2×8×12
m2=16