If 5 men can paint a wall 100 metres long in 10 days of a 8 hours each. In how many days of 6 hours each will 8men paint a wall 30 metres long?
  1. 5
  2. 2.5
  3. 1.5
  4. 10

A
10
B
2.5
C
5
D
1.5
Solution
Verified by Toppr

Total hours in 10 days =10×8=80 hours
Total man-hours needed for paint 100 m wall =5×8=40 man-hours.
Man-hours needed for 1 meter wall painting=400/100=4 man-hour.
Now,
30×4=120 m-h to do 30 meters.
120 m-h/8 men = 15 hours
15 hr/6 hr/day =2.5 days.

Was this answer helpful?
0
Similar Questions
Q1
If 5 men can paint a wall 100 metres long in 10 days of a 8 hours each. In how many days of 6 hours each will 8men paint a wall 30 metres long?
View Solution
Q2
If 16 men can build a wall of 52m long in 25 days working for 8 hours a day, in how many days can 64 men build a similar wall of 260m long working for 10 hours a day?
View Solution
Q3

40 men can build a road in 10 days, working 5 hours a day. In how many days will 30 men, working 8 hours a day, complete the road?


View Solution
Q4
Five Men can paint a building in 20 days, 8 Women can paint the same building in 25 days and 10 Boys can paint it in 30 days. If a team has 2 Men, 6 Women and 5 Boys, how long will it take to paint the building?
View Solution
Q5
A wall of 100 metres can be built by 7 men or 10 women in 10 days. How many days will 14 men and 20 women take to build a wall of 600 metres?
View Solution