Work done by A in 1 day =112
Work done by B in 1 day =120
Work done by A and B together in 1 day =112+120
=5+360=860=215
Work done by A and B together in 3 days =215×3=25
Remaining Work =1−25=35
Number of days taken by B to finish the remaining work =35120=35×201
=12 days.