Work And Time

Work From Days

Work from Days section will ask you questions in which you will have to calculate the amount of work that we can perform in some time. In a similar manner to the concept of days from work, the work from days section is easily solved by the application of some basic concepts and the formulae that we will develop. Here we have solved examples and all the important concepts that you may have to answer while solving this section. Let us see.

Suggested Videos

Play
Play
Play
previous arrow
next arrow
previous arrownext arrow
Slider

 

Work from Days

Let us start by developing the formula for this section.

First, we have the formula of the work. Where work is the numerical value of the task.  Work =  Number of days (Time) (T or D) × Number of men (M). In other words, W = D × M.

Suppose w1 is the work done in the first case and w2 in the second case. Also, let us suppose that T1 is the number of days that the first person takes and T2 is the number of days that the second term takes. Also, let N1 and N2 represent the number of people that undertake each task respectively. Then the ratio of the work done in the first task to the work done in the second task is equal to w1/w2 = (T1 × N1)/(T2 × N2). Let us see some examples of getting work from days.

Solved Example

Example 1: Ten people can cut 20 trees in 2 days. If twenty people work for two months, then how many trees will be cut during this time?

A) 1330 trees               B) 1223 trees            C) 1220 trees               D) 1222 trees

Answer: We will use the formula w1/w2 = (T1 × N1)/(T2 × N2) that we have developed just above. Here w1 = 20, T1 = 2 and N1 = 10.

Similarly, we have w2 = ? , T2 = 61 days, and N2 = 20. Substituting these  values in the equation above, we have:

w1/w2 = (T1 × N1)/(T2 × N2). In other words we can say: 20/w2 = (2×10)/(61×20).

Solving this we can say that w2 = 1220 trees.

We can use the same formula to solve similar questions.  Let us now see an important concept that will simplify a lot of our problems. The concept of efficiency in work. Hence the correct option is C) 1220 trees.

Efficiency Of Work

Work from Days

The efficiency is the amount of work that a person can do in some certain time.  For example, consider the following example:

Example 2: What is the efficiency of a person who finishes his job in 5 days?

Answer: As per the question, the number of days this person takes to complete the work = 5
Therefore we can say that he does 1/5th of the work per day. This when we convert it into percentage = 100/5 = 20%. Therefore, his efficiency is 20%.

We can use the efficiency to solve many problems in a very short time. Let us see how.

Example 3: A person ‘A’ can do a job in 10 days. Another person ‘B’ can do the same job in 5 days. In how many days will they complete this job if they work together?

Answer: As per the question, we have A’s efficiency = 10% and B’s efficiency = 20%.
Therefore when they work together, their efficiency  is = A+ B = 10 + 20 = 30%
This means, in one day A and B together can do 30% of work. Therefore, the number of days it will take A and B together to do 100% of the work = 100/30 = 3.33 days.

Some Solved Examples

Example 4: A and B can do a job in 8 days. B and C can do the same job in 12 days. When A, B, and C work together, they can do the same job in 6 days. In how many days can A and C complete this job?

Answer: As per the question we have:
The combined efficiency of A and B is = (A+B’s) efficiency = 12.5%
Also, we have: B+C’s efficiency = 8.33%
And A+B+C’s efficiency = 16.66%
Now we need to find A + C. Let us see how to solve this:

Consider, the expression 2(A+B+C), we can write it as = (A+B) + (B+C) + (C+A)
Therefore we have 2(16.66) = 12.5+ 8.33 + (C+A)
And hence we have: C+A = 12.49 = 12.5%
Therefore, the time that A and C take = 100/12.5 = 8 days.

Example 5: A person A is twice as efficient as another person B. The person A can complete a job 30 days before B. If they work together, how long will it take them to finish the job?

Answer: Let the efficiency of B = x and thus the efficiency of A = 2x.
Since the person A takes 30 days to complete a job, the person B will take 60 days to complete the same job.

A’s efficiency = 1/30 = 3.33%
B’s efficiency = 1/60 = 1.66%
Therefore there combined efficiency for this job = 3.33% + 1.66% =  5% of the job in 1 day.
So they can complete the whole job in 20 days (= 100/5 days).

Practice Questions

Q 1: A and B together can complete a task in 20 days. B and C together can complete the same task in 30 days. A and C together can complete the same task in 30 days. What is the respective ratio of the number of days taken by A when completing the same task alone to the number of days taken by C when completing the same task alone?

A) 3:1                  B) 3:2                  C) 1:3                  D) 2:3

Ans: C) 1:3

Q 2: A does 80% of a  work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

A) 37 (1/2)                 B) 36                   C) 39 (1/2)                        D) 40

Ans: 37 (1/2)

Share with friends

Customize your course in 30 seconds

Which class are you in?
5th
6th
7th
8th
9th
10th
11th
12th
Get ready for all-new Live Classes!
Now learn Live with India's best teachers. Join courses with the best schedule and enjoy fun and interactive classes.
tutor
tutor
Ashhar Firdausi
IIT Roorkee
Biology
tutor
tutor
Dr. Nazma Shaik
VTU
Chemistry
tutor
tutor
Gaurav Tiwari
APJAKTU
Physics
Get Started

2 responses to “Work From Days”

  1. shubh says:

    ans for last ques. is 38.5

Leave a Reply

Your email address will not be published. Required fields are marked *

Download the App

Watch lectures, practise questions and take tests on the go.

Customize your course in 30 seconds

No thanks.